On December 18, 2020, Nexter, Thales and Arquus, as part of the temporary grouping of companies (GME) EBMR (Engins Blindés Multi-Rôles), presented the 128th GRIFFON planned for 2020 to the French Delegation for Armaments (DGA). Under the terms of the SCORPION program, and despite an unprecedented health crisis that profoundly affected production, the three manufacturers were able to take the challenge and meet their contractual objectives.
After this step, the last GRIFFONs will have to be submitted to the verification operations carried out by the DGA's quality department. The vehicles will then be transported to the Canjuers site where the Army will proceed to take them into account; it is then that the DGA will formally receive them. To date, 90 GRIFFON have completed this route, adding to the 92 GRIFFON delivered in 2019. From January 2021, the last vehicles that left the production line in December will join them in the regiments, catching up very early in 2021 with the delay due to the health crisis.
From March 2020, Covid-19 has indeed strongly disrupted the industrial organization of the program. The site of Roanne, where the GRIFFON and JAGUAR are assembled, was forced to suspend its activity from March 20 to 30 in order to allow the installation of a structure adapted to the resumption of the activity under maximum safety conditions.